Project Phasing
2008
Phase I - Traffic Signalization work to occur in summer and Fall 2008 along University Boulevard and Beaver Grade Road ► Completed
Phase IA - Demolish Carnot Building ► Completed
Phase II - Bid High School Construction Project in Fall 2008. High School to be occupied by November 2010 ► Completed
2009
Phase II - High School Construction work continues throughout the year ► Completed
Phase III - Middle School Design created ► Completed
2010
Phase II - High School Construction finishes by November
Phase III - Bid Middle School Renovation Project in early 2010
Phase III - Begin Middle School Renovations during summer vacation. Selected exterior work will continue until after high school completion and move
2011
Phase III - Major Middle School Renovations begin in January
2012
Phase III - Middle School Renovation complete for 2012-13 school year
Phase IIIA - Demolish existing Middle School Building
Phase IIIA - Complete all site work including landscaping and parking lots for 2012-13 school year